Explained
How environmental assessments work in BC
Big mines, pipelines, plants and other major projects in BC need an environmental assessment certificate before they can be built. Here are the seven phases, where the public gets a say, how long ministers have to decide and what a certificate does and doesn't allow.
Before a major project in BC can be built, it usually needs an environmental assessment (EA). The province's Environmental Assessment Office (EAO) runs it under the 2018 Environmental Assessment Act. It looks at a project's possible environmental, social, economic, health and cultural effects.
Which projects need one
A project needs an EA if it is a "reviewable project." That happens in one of three ways:
- It meets the thresholds in the Reviewable Projects Regulation, such as production volume, storage capacity or area disturbed.
- The minister designates it, for example after a request from the public. The minister can do this if the project could have a significant adverse effect and hasn't substantially started.
- The company asks for it to be reviewed.
A reviewable project needs an EA certificate, or an exemption, before construction starts.
The seven phases
The EAO's process has seven phases:
- Early engagement. The project is described and people give early feedback. First Nations that want to take part as participating Indigenous nations say so here.
- Readiness decision. Whether the project goes ahead to a full EA. Rarely, it is exempted or ended here.
- Process planning. A process order sets the scope, methods and who does what, when.
- Application development and review. The company prepares its application and it is reviewed.
- Effects assessment and recommendation. The EAO drafts an assessment report and a draft certificate with conditions.
- Decision. Two ministers decide.
- Post-certificate. Compliance checks, audits and any changes to the certificate.
Where the public has a say
There are four public comment periods, the EAO says, starting with early engagement. A Community Advisory Committee is set up during process planning to advise on local effects. The public can also comment on the draft report and draft certificate before they go to ministers.
The decision
Under the 2018 Act, ministers have 30 days from referral to decide. They must consider the assessment report and the EAO's recommendations, and publish their reasons. There is no appeal under the Act, but decisions can go to court through judicial review.
Where a project also needs a federal assessment, the two governments aim for one project, one assessment. Each government still makes its own decision.
What a certificate means
A certificate is not a permit to build. The project still needs its other provincial, federal and local permits, and those can't be issued until the certificate is.
Under the 2018 Act, a project has up to 10 years to substantially start, with one extension of up to five years. A certificate can be cancelled if the project isn't running 20 years after it was issued.
Project documents and comment periods are posted on the EAO's project site, EPIC.
Sources
- Environmental assessment process (Province of British Columbia)
- Environmental assessments: frequently asked questions (Province of British Columbia)
- Public participation guidance (Province of British Columbia)
First drafted with AI from the sources above, then checked and approved by an editor. Spotted a mistake? Tell us.
Quoted or named here? Tell us if we got it wrong, and we'll look at it and correct it if needed. Last reviewed November 23, 2026.
Next story What the BC Major Projects Inventory tells you Every quarter the province lists BC construction projects worth $15 million or more. Here is what gets in, what the statuses mean, how the regions are split and the limits to keep in mind when you use it to find work.